Client Conway Corporation
Scope Of Work Expansion and Upgrade of the Water Treatment Facilities
Schedule New facility online 2005 Upgraded facility in service 2006

Project Detail

The original Gleason Water Treatment Plant was constructed in 1963 with expansion in 1967 and 1986 increasing the plant capacity to 15-MGD.

Most recently, MWY completed an expansion and upgrade project. The new Roger Q Mills facility went online in 2005. The upgraded existing facility was placed into service in February 2006. The total capacity of the plant is now 32-MGD.

The improvements include a sedimentation basin and filters rated at 8-MGD, a 12,800 sq. ft. Operations- Chemical Feed Building, a 2-MG treated water reservoir, and a new pump station. Upgrading the existing plant was also a part of the project.