SILENT GROVE ROAD & DRAINAGE IMPROVEMENTS

GROWING NEIGHBORHOOD BENEFITS
Client City of Springdale
Location Springdale, Arkansas
Schedule Completed in 2006

Project Detail

Accommodating the heavier traffic flows and natural stormwater associated with the rolling topography of the area was a primary factor in the design of this street improvement project.

The scope included widening and reconstructing approximately 3,000 linear feet of the existing road from a two-lane road to a three-lane collector street.

An existing natural channel conveying off-site drainage flows runs parallel with and near to the existing road. A primary consideration of the design was accommodating the channel.

CLIENT:
City of Springdale, Arkansas

COST:
Opinion of Probable Cost: $1,600,000
Construction Bid: $1,445,994
Final Construction Cost:     $1,323,987

COMPLETED:
Construction Began 2004
Completed in 2006